Dhaliwal JS, Dhillon J. Memetic binary differential evolution to solve wind–thermal profit based unit commitment problem. Appl Soft Comput 2022. [DOI: 10.1016/j.asoc.2022.109105] [Citation(s) in RCA: 1] [Impact Index Per Article: 0.5] [Reference Citation Analysis] [Track Full Text] [Journal Information] [Subscribe] [Scholar Register] [Indexed: 11/16/2022]
|
2
|
A Project-Scheduling and Resource Management Heuristic Algorithm in the Construction of Combined Cycle Power Plant Projects. COMPUTERS 2022. [DOI: 10.3390/computers11020023] [Citation(s) in RCA: 1] [Impact Index Per Article: 0.5] [Reference Citation Analysis] [Abstract] [Track Full Text] [Subscribe] [Scholar Register] [Indexed: 11/16/2022]
Abstract
Given the growing number of development projects, proper project planning and management are crucial. The purpose of this paper is to introduce a heuristic algorithm for scheduling a power plant project construction and project resource management to determine the size of project buffers and feeding buffers. This algorithm consists of three steps: 1. estimating the duration of project activities; 2. determining the size of the project buffer and feeding buffers; and 3. simulating the mentioned algorithm, which will be explained below. Innovations of this research are as follows: estimating the exact duration of project activities by using a heuristic algorithm, in addition to determining the buffer size; calculating both project buffer and feeding buffers; and applying the algorithm to implement an ACC used in combined cycle power plant projects as a numerical example. In order to evaluate the proposed algorithm, inputs from this project were run through several algorithms recently presented. The results showed that a suitable amount of buffers can be allocated for projects using this algorithm.
Collapse
|
3
|
Zohrehvandi S, Vanhoucke M, Khalilzadeh M. A project buffer and resource management model in energy sector; a case study in construction of a wind farm project. INTERNATIONAL JOURNAL OF ENERGY SECTOR MANAGEMENT 2020. [DOI: 10.1108/ijesm-10-2019-0025] [Citation(s) in RCA: 6] [Impact Index Per Article: 1.5] [Reference Citation Analysis] [Abstract] [Track Full Text] [Subscribe] [Scholar Register] [Indexed: 11/17/2022]
Abstract
Purpose
This study aims to introduce an efficient project buffer and resource management (PBRM) model for project resource leveling and project buffer sizing and controlling of project buffer consumption of a wind power plant project to achieve a more realistic project duration.
Design/methodology/approach
The methodology of this research consists of three main phases. In the first phase of the research methodology, resource leveling is done in the project and resource conflicts of activities are identified. In the second phase, the project critical chain is determined, and the appropriate size of the project buffer is specified. In the third phase of the methodology, buffer consumption is controlled and monitored during the project implementation. After using the PBRM method, the results of this project were compared with those of the previous projects.
Findings
According to the obtained results, it can be concluded that using PBRM model in this wind turbine project construction, the project duration became 25 per cent shorter than the scheduled duration and also 29 per cent shorter than average duration of previous similar projects.
Research limitations/implications
One of the major problems with projects is that they are not completed according to schedule, and this creates time delays and losses in the implementation of projects. Today, as projects in the energy sector, especially renewable projects, are on the increase and also we are facing resource constraint in the implementation of projects, using scheduling techniques to minimize delays and obtain more realistic project duration is necessary.
Practical implications
This research was carried out in a wind farm project. In spite of the initial plan duration of 142 days and average duration of previous similar projects of 146 days, the project was completed in 113 days.
Originality/value
This paper introduces a practical project buffer and resource management model for project resource leveling, project buffer sizing and buffer consumption monitoring to reach a more realistic schedule in energy sector. This study adds to the literature by proposing the PBRM model in renewable energy sector.